East Trails Middle School
East Trails Middle School is a key component of LSR7 Board-approved plans to move sixth grade to middle school.
Built on land purchased by the district for this purpose in 2012, the 180,000 square foot East Trails Middle School will incorporate future-ready design and provide learning for 1,200 students. Our grades 6-8 middle school model debuts in the 2022-23 school year.
Project Information
See Project Progress
January 2022
February 2021
February 2021
February 2021
February 2021
February 2021
March 2021
March 2021
April 2021
May 2021
May 2021
May 2021
June 2021
June 2021
June 2021
June 2021
August 2021
August 2021
August 2021
August 2021
August 2021
August 2021
August 2021
October 2021
December 2021
December 2021
December 2021
December 2021
December 2021
December 2021
January 2022
June 2022
June 2022
June 2022
June 2022
Total Budget: $72 Million
Location: 1001 SE Bailey Road, Lee's Summit, MO 64081
Construction Start Date: September 2020
Construction Completion Date: July 2022
Construction Manager: McCownGordon Construction
Architect: DLR Group
Middle School Renovations
Renovations at R-7’s three existing middle schools will improve circulation and create additional space for programs such as music and art in order to prepare schools to host sixth grade beginning in the 2022-23 school year.
Bernard Campbell Middle School
Pleasant Lea Middle School
Summit Lakes Middle School